£1.5m investment at Temple Quarry



Whitemountain has invested over £1.5m to replace and relocate the primary crushing plant at Temple Quarry. The works consisted of refurbishment and modification of an existing dump chute, construction of a 12m high Gabion retaining wall and installation of a new Feeder and Metso C130 Jaw crusher, with remote control workstation.

The majority of the works were carried out off-line, allowing production to continue during construction, before final linking to the secondary plant. The project was completed with the arrival of a new Komatsu HD465 rigid dump truck to match the new primary plant’s production demand.

These upgrades will ensure continued quality, increased production outputs and improved plant reliability at Temple Quarry.


Product calculator icon Product calculator icon hover